-CITE-
16 USC Sec. 838g 01/26/98-EXPCITE-
TITLE 16 - CONSERVATION
CHAPTER 12G - PACIFIC NORTHWEST FEDERAL TRANSMISSION SYSTEM-HEAD-
Sec. 838g. Schedules of rates and charges for sale of Federal power
and transmission of non-Federal power; confirmation and
approval; criteria for modification and establishment-STATUTE-
Schedules of rates and charges for the sale, including
dispositions to Federal agencies, of all electric power made
available to the Administrator pursuant to section 838f of this
title or otherwise acquired, and for the transmission of
non-Federal electric power over the Federal transmission system,
shall become effective upon confirmation and approval thereof by
the Secretary of Energy. Such rate schedules may be modified from
time to time by the Secretary of Energy, acting by and through the
Administrator, subject to confirmation and approval by the
Secretary of Energy, and shall be fixed and established (1) with a
view to encouraging the widest possible diversified use of electric
power at the lowest possible rates to consumers consistent with
sound business principles, (2) having regard to the recovery (upon
the basis of the application of such rate schedules to the capacity
of the electric facilities of the projects) of the cost of
producing and transmitting such electric power, including the
amortization of the capital investment allocated to power over a
reasonable period of years and payments provided for in section
838i(b)(9) of this title, and (3) at levels to produce such
additional revenues as may be required, in the aggregate with all
other revenues of the Administrator, to pay when due the principal
of, premiums, discounts, and expenses in connection with the
issuance of and interest on all bonds issued and outstanding
pursuant to this chapter, and amounts required to establish and
maintain reserve and other funds and accounts established in
connection therewith.-SOURCE-
(Pub. L. 93-454, Sec. 9, Oct. 18, 1974, 88 Stat. 1377; Pub. L.
95-91, title III, Sec. 301(b), 302(a)(1)(D), Aug. 4, 1977, 91 Stat.
578.)-TRANS-
TRANSFER OF FUNCTIONS
''Secretary of Energy'' substituted in text for ''Secretary of
the Interior'' and ''Federal Power Commission'' pursuant to Pub. L.
95-91, Sec. 301(b), 302(a)(1)(D), which are classified to sections
7151(b) and 7152(a)(1)(D) of Title 42, The Public Health and
Welfare.
Federal Power Commission terminated and its functions, personnel,
property, funds, etc., transferred to Secretary of Energy (except
for certain functions transferred to Federal Energy Regulatory
Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293
of Title 42.
Functions of Secretary of the Interior with respect to Bonneville
Power Administration transferred to Secretary of Energy by section
7152(a)(1)(D), (2) of Title 42, with Bonneville Power
Administration to be preserved as a distinct organizational entity
within Department of Energy and headed by an Administrator.-SECREF-
SECTION REFERRED TO IN OTHER SECTIONS
This section is referred to in section 839e of this title.