The Cost Verification Process for the Slice True-Up Adjustment Charge is a new annual public process developed under the Tiered Rates Methodology (TRM) that will permit Slice customers, other BPA customers, and other interested parties to review the Slice True-Up Adjustment Charge and to assess whether BPA has correctly calculated the amount of each expense or revenue credit subject to the Slice True-Up Adjustment, and whether the final Slice True-Up Adjustment contains only those expenses and revenue credits permitted to be included in, and does not contain any expenses or revenue credits excluded from, the Slice Rate pursuant to the TRM; see section 2.7.5.1 and Attachment A of the TRM.

See our Background page for more information.

Meeting
Date Topic and Materials
Meeting cancelled - will be rescheduled for late May 2013
Slice True-up 101 Webinar Training Session
This will be a web-based "Live Meeting" training session to review and address questions about the Slice True-up Adjustment Charge, as provided in the Tiered Rates Methodology and presented in Quarterly Business Reviews.
 
 
Phone bridge and Live Meeting information will be posted to BPA’s event calendar prior to the meeting.
Cost Verification Process for FY 2012
Dates (estimated) Agenda
November 21, 2012 or earlier

Notification to Slice Customers of the Slice True-Up Adjustment for the Composite Cost Pool True-Up Table
BPA to post Composite Cost Pool True-Up Table containing actual values and the Slice True-Up Adjustment

FY-12 Composite Cost Pool True-Up Table

December 6th Meeting Materials:

​December 14, 2012

​Deadline for customers to submit questions about actual line items in the Composite Cost Pool True-Up Table with the Slice True-Up Adjustment for inclusion in the Agreed Upon Procedures (AUPs) Performed by BPA external CPA firm (customers have 15 business days following the posting of Composite Cost Pool Table containing actual values and the Slice True-Up Adjustment

Comment Period Closed

​December 31, 2012

​BPA posts a draft list of AUP tasks to be performed (Attachment A does not specify an exact date)

​January 11, 2013

​The Cost Verification Process second comment period is closed.  No AUP tasks for further consideration have been identified. In as much the workshops, comment periods, and draft responses will not be necessary and this concludes the Cost Verification Process for FY 2012.

 