‚ÄčRaymond-Cosmopolis 115-kV Transmission Line Rebuild  (DOE/EA-1425)
Grays Harbor and Pacific Counties, Washington

PROJECT DESCRIPTION:
Bonneville Power Administration (BPA) proposes to rebuild an existing 115-kV transmission line, between Raymond and Cosmopolis, roughly parallel to Hwy 101. Most of the 18.3-mile long transmission line would remain within the existing right-of-way, but some structures would be moved due to environmental or engineering constraints.

CONTACT:
For further information on this project, please contact Kimberly St.Hilaire, BPA Environmental Lead.

DOCUMENTS:

FINAL EA / FONSI: 
Public Letter              (09/05/2003)
Final EA and FONSI    (08/22/2003)
Final EA and FONSI formatted for printing

PRELIMINARY EA
Preliminary EA (Abridged)      (01/28/2003)
Public Letter                        (01/21/2003)
Comment Form                   (03/28/2002)