PROJECT DESCRIPTION:
The Bonneville Power Administration (BPA) rebuilt its Alvey-Fairview 230-kilovolt Transmission Line between Eugene and Coquille, Oregon. To understand the potential environmental impacts of this proposal, BPA prepared an environmental assessment (EA). Two alternatives were studied in the EA: to rebuild the line or to not rebuild the line, and continue on with current operation and maintenance practices. The EA described anticipated impacts to natural and human resources and included mitigation measures that will help avoid or minimize impacts.

CURRENT STATUS:
BPA issued the final EA and Finding of No Significant Impact (FONSI) for the project in 2014 and decided to proceed with the Proposed Action. Project construction is began in June 2014 and was completed in December 2015.

PROJECT SCHEDULE:
Scoping comment period:
Scoping public meeting:
Scoping public meeting:
Draft EA comment period:
Final EA:
Finding of No Significant impact:
Construction start:
Construction completed:

CONTACT: 
For environmental information, contact:
Doug Corkran
Environmental Protection Specialist
Bonneville Power Administration - ECT-4
P.O. Box 3621
Portland, OR 97208-3621

For project information, contact: 
James Semrau
Project Manager
Bonneville Power Administration
P.O. Box 61409
Vancouver, WA  98666-1409

DOCUMENTS:


November 15, 2011 through December 28, 2011
November 30, 2011 in Sutherlin, Oregon
December 7, 2011 in Cottage Grove, Oregon
February 7, 2014 through March 3, 2014
April 21, 2014
April 21, 2014
Summer 2014/2015
December 2015



Toll-free:      800-622-4519
Direct line:   503-230-7646
Email:         dfcorkran@bpa.gov



Toll-free:      800-622-4519
Direct line:   360-619-6629
Email:         jesemrau@bpa.gov

PROJECT UPDATE:
Public Letter - Notice of Construction    (03/31/2015)

FINAL EA:
Public Letter                               (05/02/2014)
FONSI and Mitigation Action Plan   (04/21/2014)
Final EA                                     (04/21/2014)

DRAFT EA:
Draft EA comments received 
Public Letter                    (02/07/2014)
Draft EA                          (February 2014)
Comment Form               (02/07/2014)

SCOPING:
Scoping comments received 
Public Letter                   (11/15/2011)
Project Map                    (06/15/2011)
Comment Form              (11/15/2011)

EA Determination Memo   (08/05/2011)