The U.S. Army Corps of Engineers (Corps) plans to construct an ecosystem restoration project at Trestle Bay.  The project would create multiple openings in the South Jetty Root, with a cumulative opening width of no more than 900 linear feet.  The openings are intended to provide adequate access into Trestle Bay for salmon and steelhead.  The project site is located in Clatsop County, Oregon, about six miles upstream of the mouth of the Columbia River.

The Bonneville Power Administration (BPA) plans to provide funding for the project.  Providing funding will help BPA meet obligations -- under the Pacific Northwest Electric Power Planning and Conservation Act of 1980 and the Federal Columbia River Power System (FCRPS) Biological Opinion -- to mitigate for the effects of the FCRPS on the listed salmon and steelhead.

CURRENT STATUS:
The Corps, in cooperation with Bonneville Power Administration, prepared an environmental assessment (EA) to help determine the potential impacts that project would have on the natural and human environment.  The Corps released the draft EA for public review and comment in March 2015, and received three comments.  The Corps prepared a final EA that includes responses to comments received.  Based on the EA analysis and mitigation measures to help lessen impacts, BPA has found that the project will not cause any significant impacts, and has issued a finding of no significant impact.

To view the final EA and the Corps' FONSI, please visit the Corps' District Announcements website at:  http://www.nwp.usace.army.mil/Media?Announcements.aspx.

To view BPA's FONSI, see the link below:

CONTACTS:
For further information:
Gail Saldana
Project Manager
U.S. Army Corps of Engineers
333 SW 1st Avenue
Portland, OR  97204

Alternatively, you may contact the BPA
environmental protection specialist
Michelle Guay
Contract Environmental Protection Specialist
Cor-Source Technology Group
Bonneville Power Administration - ECF-4
P.O. Box 3621
Portland, OR  97208-3621
or
Donald L. Rose
Supervisory Environmental Protection Specialist
Bonneville Power Administration - ECF-4
P.O. Box 3621
Portland, OR  97208-3621

DOCUMENTS:

Bonneville Power Administration FONSI:
FONSI

Army Corps of Engineers Draft and Final EA and FONSI:
Final Feasibility Study and EA
Draft Feasibility Study and Draft EA



Email:            gail.l.saldana@usace.army.mil
Direct line:      503-808-4781
FAX:               503-808-4756




Toll-free:         800-622-4519
Direct line:      503-230-3459
Email:             mxguay@bpa.gov




Toll-free:          800-622-4519
Direct line:       503-230-3796
Email:             dlrose@bpa.gov

 



(09/10/2015)


(March 2015)
(July 2010)